The risk is not that the design changes; it is that the site team, client and designer work from different revisions and interpret the status of a decision differently.
A single issue register
- The document reference, title and discipline.
- The revision number, date and purpose of issue.
- Recipients and confirmation of transmission.
- The status of the previous revision and the rule for withdrawing it from use.
Technical query workflow
- Record the question, location and reference to the design documentation.
- Assess the impact on safety, cost, programme and interfacing design decisions.
- Assign an owner for the response and a control date.
- Issue a formal response or a new document revision.
- Confirm that the site team received the decision and close the query.
Change control
- Distinguish a request for information from a proposal to change the design.
- Do not allow work to proceed from a draft decision without a defined status.
- Link every change to its basis, approval and affected documents.
- Preserve the history so the applicable decision can be reconstructed for any given date.
What the design team gains
A controlled revision and query system reduces the risk of building from superseded drawings, makes accountability transparent and turns changes from an email chain into a managed process.