A certificate alone does not prove where a material was used. A reliable system links the delivery, batch, inspection, test results and the specific structure or system in which the material was installed.
Minimum traceability chain
- Register the delivery and its batch identifier.
- Check the accompanying documents and the condition of the material.
- Record sampling and test results where applicable.
- Identify the actual area or system where the material was used.
- Link the record to the acceptance record, as-built drawing and final dossier.
Common breaks in traceability
- The same material is described differently across registers.
- The certificate is stored separately and is not linked to the batch.
- The place of use is not recorded.
- A test result arrives after the work has been closed out and is never formally addressed.